Page 115 - claims information pack ebook_e
P. 115

Guidelines for presenting claims for clean up and preventive measures









                                                                4.5       The costs incurred and the relationship
                    Example                                          between those costs and the benefits derived or
                                                                     expected, should be proportionate. For example,
                    A port authority instructs a spill response      a high degree of cleaning, beyond removal of
                    contractor, resident in the port with whom it    bulk oil, of exposed rocky shores inaccessible
                    has good working relations but no contract, to   to the public is rarely justified, since natural
                    respond to a spill from a tanker a few miles off   cleaning by wave action is likely to be more
                    the coast where the tanker has run aground.      effective. On the other hand, thorough cleaning
                    It is winter with low water temperatures and     may be necessary in the case of a public
                    a substantial amount of heavy fuel oil has       amenity beach, particularly immediately prior
                    been spilled which threatens the port and        to or during the holiday season.
                    surrounding coastline. The contractor is
                    ordered to apply dispersant onto the oil in an   4.6       While it is understood that response
                    effort to prevent it reaching the coast but as   organisations often find themselves compelled
                    a result of onshore winds, the oil soon comes    by political pressure and concerns expressed
                    ashore and has to be cleaned up there.           by the public and the media to adopt measures
       10                                                            which are not technically reasonable, such
                    On the advice of their experts, the insurer      actions are unlikely to qualify for compensation.
                    and the 1992 Fund conclude that this element     For example, increasing the size of the
                    of the response was unreasonable. This is        workforce involved in shoreline clean up beyond
                    because it should have been foreseen that        the numbers that can be effectively managed
                    under those particular conditions, dispersants   or continuing operations long after they can be
                    could not have been effective. As there is no    justified on technical grounds, are unlikely to
                    contract with the port authority, the contractor   be considered reasonable. Whenever possible
                    presents a claim directly to the shipowner’s     the 1992 Fund will, at the earliest opportunity
                    insurer and the 1992 Fund but faces the          notify the authorities, in writing, that in the
                    possibility of having compensation denied even   opinion of the 1992 Fund, based on advice of
                    though the instructions of the port authority    their experts on site, such a situation has arisen
                    were being followed. Had a contract been in      and that compensation for measures taken
                    place, the contractor would have been paid by    after a certain date may not be available. This
                    the port authority. However, it is unlikely that   does not mean that authorities must follow
                    a claim submitted by the port authority for      this advice. There is no question that it is for
                    reimbursement of the cost of the contractor      Member States to conduct the response in any
                    would be successful since the measures           way they see fit. However, in the light of such
                    would be judged to have been unreasonable.
                                                                     notification, a Member State should be aware
                                                                     that it might not be possible for the 1992 Fund
                                                                     to reimburse costs for measures considered to
                                                                     be unreasonable after a certain date.
   110   111   112   113   114   115   116   117   118   119   120