Page 142 - claims information pack ebook_e
P. 142

Guidelines for presenting claims for clean up and preventive measures









         5.2 Marine Pollution Responders Ltd (Example 2 of 3 worksite spreadsheets linked to contractor’s overall costs)
         Worksite 2 Rocky Cove
            5.2 Marine Pollution Responders Ltd (Example 2 of 3 worksite spreadsheets linked to contractor’s overall costs)
            WS2 Rocky Cove
                       Unit                                                Number   Unit   Rate   Claim
                       cost   12 June   13 June   14 June   15 June   16 June   17 June   18 June   19 June   20 June   21 June   22 June   23 June   24 June   25 June   26 June
            I Personnel                                                                      £
              Beach-master   350           1   1   1   1   1      1   1   1   8   Man days   100%  2 800

                       350           1   1                 1   1           4     Man days   150%  2 100

              Supervisors   200            2   2   2   3   3      2   2    16    Man days   100%  3 200

                       200           2   2                 2   2           8     Man days   150%  2 400

              Labourers   120              40   40   40   60   60   40   20   300   Man days   100%  36 000

                       120           25   40               40   20         125   Man days   150%  22 500

              Meals    8.5                                                 461   Man days   100%  3 919

            II Equipment                                                         Personnel subtotal   72 919

              Cars     55            2   2   2   2   2   2   2   2   2   2   2   1   23   Days   100%  1 265

              Vans     95            2   3   3   3   3   4   4   3   2   3   2   32   Days   100%  3 040

              HP washers   50        5   6   8   8   8   9   9   8   4   8   4   77   In use   100%  3 850

                       50               2                  1   5   1   5   14    Standby   50%   350

            III Materials                                                        Equipment subtotal   8 505

              Sorbent mats   7.5     50   50   50   50   50   250   400   250   200   95   1 445   kg   100%  10 838

              Plastic bags    4      2.5  2.5  2.5   2.5  2.5  12.5   20   10   10   5   70   Bags x 10   100%  280   37

              Gloves    2            28   43   43   43   43   64   64   43   23   43   23   460    Prs   100%  920

              Cotton gloves   0.5    28   43   43   43   43   64   64   43   23   43   23   460   Prs    100%  230

              Tivek suit   4.5       28   43   43   43   43   64   64   43   23   43   23   460   Tivek suits    100%  2 070

              Waterproofs   12                43   43   64   64   43   23   280   Waterproofs   100%  3 360

              Boots    6.5           28   15     12   64                   119   Boot prs    100%  774

                                                                                 Materials subtotal   18 471

                                                                                 WS2 SUBTOTAL:   99 895

                                            IOPC/APR15/4/1, Annex, Attachment, Page 7
         5.3 Marine Pollution Responders Ltd (Example 3 of 3 worksite spreadsheets linked to contractor’s overall costs)
         Worksite 3 Cobble Bank
            5.3 Marine Pollution Responders Ltd (Example 3 of 3 worksite spreadsheets linked to contractor’s overall costs)
            WS3 Cobble Bank
                     Unit                                                   Number   Unit   Rate   Claim
                     cost
          I Personnel     12 June   13 June   14 June   15 June   16 June   17 June   18 June   19 June   20 June   21 June   22 June   23 June   24 June   25 June   26 June   £
           Beach-master   350             1   1   1   1   1       1         6     Man days   100%   2 100
                     350               1     1                1     1         4   Man days   150%   2 100
             Supervisors   200               1    1     1     2     2     1         8   Man days   100%   1 600
                     200                 1                    1             2     Man days   150%   600
             Labourers   120                 10    20     10     20     20        5         85   Man days   100%   10 200
                     120                 10                   10            20    Man days   150%   3 600
             Meals   8.5                                                    125   Man days   100%   1 063
            II Equipment                                                          Personnel subtotal   21 263
           Excavator     300              1     1     1     1     1     1     1     1     1     1           10   Days   100%   3 000
            Cars     55            1   1   1   1   1   1   1   1   1         9    Days     100%   495
            Vans     95               1   1   2   1   2   2   1             10    Days     100%   950
            III Materials                                                         Equipment subtotal   4 445
           Sorbent booms     25                 108                 56           12           176   m   100%   4 400
            Sorbent mats   7.5              50   50     150     150     150     250   100     50      5         955   kg   100%   7 163
            Plastic bags    4             2.5  2.5   2.5   2.5   2.5   2.5   2.5   2.5     2.5  2.5         25   Bags x 10   100%   100
            Gloves    2             1   12   12   22   12   23   23   12   1   7         125   Prs   100%   250
            Cotton gloves   0.5             1   12   12   22   12   23   23   12   1   7         125   Prs    100%   63
            Tivek suit   4.5            1   12   12   22   12   23   23   12   1   7         125   Tivek suits    100%   563
            Waterproofs   12                  22   12   23   23   12   1         93   Waterproofs    100%   1 116
            Boots    6.5              1     11      10   12   11            45    Boot prs    100%   293
                                                                                  Materials subtotal   13 946
                                                                                  WS3 SUBTOTAL:    39 654



                                              IOPC/APR15/4/1, Annex, Attachment, Page 8